The order to do it in
The work is spread over a fortnight. The day itself should be dull.
A stocktake that is exciting on the morning was prepared badly.
Everything below is deliberately front-loaded, because every one of these problems is
cheap to fix a week out and expensive to fix with twelve people standing around. If your
count has to land on a fixed date, there is a
separate run-up for 30 June.
2 WEEKS
Tidy and label the locations
Bins named, labels up, at a height a person can reach and read. This is the job
that always takes longer than anyone thinks, which is why it goes first and not
last.
1 WEEK
Check the part file, properly
Export it and look at it. Duplicated codes, parts that were deleted in 2019,
descriptions that are blank, barcodes in the part-number column. Every one of these
is a five-minute fix now and a person standing in an aisle later.
THE WEEK BEFORE
Let people look things up for real
Have the counters scan actual stock and actual labels during their normal week, with
no count running. Bad data and unreadable labels surface while there is still time
to do something about them. This is the step most people skip and the one that
saves the most.
NIGHT BEFORE
Charge everything, including the spares
Every device and every spare battery. A scanner that dies at 2pm costs you an
operator for the rest of the day, and the flat one is always the one somebody left
out of the cradle.
THE MORNING
Load the data once, then start
Final import of parts and locations first thing, then begin. Reloading reference
data halfway through a count is the one thing guaranteed to make the totals
arguable.
DURING
Watch the areas, and watch the people
Which areas are finished, what has stopped, and how much each person has actually
counted. It is not a race — somebody in bulk storage will always out-count
somebody in small parts, and the fast one is not the better one. But it does show
you the person who is not counting at all.
Why the per-operator graph exists at all. We built it for a company counting
across a weekend, with everyone on penalty rates. More than a dozen people, a system
none of them had used before, and us on site the whole weekend in case it went wrong.
It was expensive before a single item had been scanned.
Almost everybody did exactly what you would hope. Eight hours
on their feet, hundreds of items each, working fairly and carefully. One man counted
four items in two hours. He had not come to count. He was
sent home before lunch, and what that saved paid for the day.
That is the whole purpose of it. Not to rank the people doing
the job properly — they are all doing the job properly, in aisles that are not
comparable. It is so the one person who is not shows up while there is still a shift
left to fix it, instead of on Monday when the invoice arrives.
That graph, and the rest of what a supervisor watches while a
count is running, is on the
Dashboard — progress by aisle and level, who has
stopped and for how long, and the counts worth a second look.